Objectives
- Repair Eroding Stream Banks
- Improve Water Quality
- Improve Habitat
- Reduce the amount of sediment in the water
- *This project WILL NOT reduce flooding
- **The North Carolina Water and Land Fund (formerly known as the Clean Water Management Trust Fund) grant of $425,000 given in February for Phases I and II.
-
Before
-
After
Estimated Cost: To Be Determined**
**The North Carolina Water and Land Fund (formerly known as the Clean Water Management Trust Fund) grant of $425,000 given in February for Phases I and II.
The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process.
Project Schedule
Project Schedule | ||
---|---|---|
Phase | Status | End Date |
Planning | Completed | January 2017 |
Design | Completed | January 2019 |
Permitting | Completed | January 2019 |
Property Easement Acquisition | Completed | January 2019 |
Bid | Completed | June 2020 |
Construction | Completed | July 2022 |
Warranty | Completed | July 2023 |