Objectives
- Repair Eroding Stream Banks
- Improve Water Quality
- Improve Habitat
- Reduce the amount of sediment in the water
- *This project WILL NOT reduce flooding
Estimated Cost: $175,000**
*includes all costs associated with this project such as planning and design, utility relocation, consultant fees, permits, construction, and landscaping.
The project team will manage the project through several phases. Specific work is conducted during each phase and public involvement is emphasized throughout the process.
Project Schedule
Project Schedule | ||
---|---|---|
Phase | Status | End Date |
Planning | Completed | March 2019 |
Design | Completed | October 2019 |
Permitting | Completed | October 2019 |
Property Easement Acquisition | Completed | January 2019 |
Bid | Completed | November 2021 |
Construction | Completed | May 2023 |
Warranty | In Progress | Spring 2024 |